Installation of Belfry Floor

Tuesday, 31st October

Paul from Taylors Foundry arrived to construct and install a new belfry floor in preparation for the installation of the steel bell frame which is now underway in Loughborough. This new floor will be just below the bell frame and will allow access to the bells for maintenance. When the timber and steel arrived, it all had to be cut to size and hauled up into the tower for fitting. Luckily we had a willing band of volunteers to help with this but even so the work took four days and is currently being completed (8th November).